← All news

20 Oct 2026

Machine translation of the Polish original. Read the original in Polish

Europe: 33.8 GW of new photovoltaics in the first half and new network charging rules for storage

Photovoltaics was the EU's largest source of electricity in June 2026. At the same time, Brussels and a growing number of countries are putting in order the network charging rules for energy storage.

Farma fotowoltaiczna o zachodzie słońca z turbinami wiatrowymi na wzgórzach i magazynem energii przy stacji
AI-generated illustration — does not show the facility described

According to the SolarPower Europe report "EU Solar Market Update: 2026 Mid-Year Analysis", published on 8 September 2026, European Union countries installed 33.8 GW of new photovoltaic capacity in the first half of the year — 1.9% more than a year earlier (33.2 GW). Poland was among the countries that recorded year-on-year growth.

Photovoltaics the largest source of electricity in June

  • in June 2026, photovoltaics supplied 25% of electricity in the EU and was the largest source,
  • since 1 March 2026, panels have produced 282 TWh, which according to SolarPower Europe saved approximately EUR 30 billion in gas imports,
  • the forecast for the whole of 2026 is 68.1 GW, i.e. 2.1% less than the record 69.6 GW in 2025 (scenarios: 62–74.1 GW).

The organisation warns that the EU is not on track to meet its 2030 targets, pointing among other things to the need for energy storage, grid expansion and stable regulation.

Network charges for storage: the direction from Brussels

In document COM(2026) 600 of 17 July 2026, the European Commission indicated that network charges for energy storage should reflect the benefits and costs that storage brings to the system. The Commission wants to have the option of adopting delegated acts with a common tariff structure. According to an overview prepared by Gramwzielone.pl, a growing number of countries are already changing their rules:

  • Germany — the regulator BNetzA's draft of 6 August 2026 envisages a capacity charge of €4–7/kW per year, with no charges on the volume of energy; protection for projects with an investment decision before 1 January 2027 and commissioning by 4 August 2029; and dynamic charges in 2030–2033; the current exemption provisions expire — following the CJEU (Court of Justice of the European Union) ruling — at the end of 2028,
  • United Kingdom — Ofgem proposes a security charge of GBP 3–25 thousand/MW in the event of an oversupply of projects — about 90 GW of storage is operating or in the connection queue, against a need of about 29 GW by 2035,
  • Poland — according to a breakdown by Energy Storage Europe, storage is not subject to double charges or double taxation.

In 2025, Europe added 13.5 GW and 26.4 GWh of electrochemical storage.

Significance for Poland

EU tariff rules for energy storage will in the coming years affect the tariffs of PSE (the Polish transmission system operator) and of distribution system operators, and thereby the business models of BESS projects. The current Polish arrangements, without double charges, remain favourable compared with the rest of Europe. The growing share of photovoltaics in the mix, in turn, confirms that the next stage of the transition is system flexibility — an area in which NRG+ develops energy storage and hybrid installation projects.

Sources

NRG+ newsletter

Occasional updates: renewables market, lease rates and new areas where we are looking for land.