Poland's largest energy storage facilities: Greenvolt builds 600 MW, PGE develops Żarnowiec and Gryfino

September saw construction start on the 600 MW / 2.4 GWh BESS Siedlce. In parallel, PGE is reporting progress on its own battery projects.

Widok z drona na budowę dużego magazynu energii: rzędy kontenerów bateryjnych, dźwig i nowa stacja elektroenergetyczna
AI-generated illustration — does not show the facility described

Greenvolt Power has begun construction of the BESS Siedlce energy storage facility in the municipality of Zbuczyn in Mazovia. The installation, with a capacity of 600 MW and a usable capacity of 2.4 GWh, is set to be the largest energy storage facility in Poland. Commercial operation is planned for the end of 2027.

Scale of the Siedlce project

  • a plot of 5.23 ha, of which about 30% will remain biologically active area,
  • BYD Energy Storage technology: 210 battery containers and 105 transformer containers,
  • connection to the PSE (the Polish transmission system operator) grid at 400 kV — P&Q is building a 400/110 kV substation and 400 kV and 110 kV cable lines, while construction work is carried out by ONDE.

Once the projects in Siedlce, Turośń Kościelna and Ełk are completed, Greenvolt will have energy storage in Poland with a combined capacity of 1 GW and 4 GWh. According to Energy-Storage.News, all three projects hold capacity market contracts from the portfolio awarded in the 2023 auction. At the end of June 2026, the company's portfolio in Poland stood at 2.4 GW.

PGE: Żarnowiec 85% complete, Gryfino under construction

The PGE Group allocated PLN 518 million to energy storage in the first half of 2026, and its future commitments for two large projects exceed PLN 1.5 billion. According to Gramwzielone.pl:

  • Żarnowiec — 263 MW and approx. 1,020 MWh, budget of approx. PLN 1.3 billion, 85% complete, completion in Q2 2027, 17-year capacity contract from 2029; the contractor is LG Energy Solution Wrocław,
  • Gryfino (Nowy Czarnów) — 400 MW and at least 800 MWh, a contract worth PLN 1.1 billion gross, completion in 2028, 17-year capacity contract; the contractors are Spec Bau Polska and El Professional,
  • approx. 190 MW of storage at the group's wind farms by 2028.

Significance for the market

Large storage facilities connected to the transmission grid are becoming a standard element of the Polish power system, and capacity market contracts continue to play a key role in financing them. The Siedlce project also shows that a 600 MW installation occupies a relatively small area — a few hectares — provided there is access to a suitable connection point. These are exactly the locations near electrical substations that NRG+ is looking for as it develops energy storage projects with capacities from 4 to 600 MW.