A September of repeated photovoltaic curtailments. PSE confirms the right to compensation

In the first three weeks of September, the transmission system operator instructed PV farms to reduce output on at least 13 days. Installation owners are in principle entitled to compensation.

Farma fotowoltaiczna w pełnym słońcu, nad polem przebiegają linie wysokiego napięcia
AI-generated illustration — does not show the facility described

In September 2026, Polskie Sieci Elektroenergetyczne (PSE, the Polish transmission system operator) issued non-market redispatching instructions, that is, instructions to reduce the output of photovoltaic installations, on 1–7 September and for six consecutive days from 16 to 21 September, in total at least 13 days in the first three weeks of the month. According to e-magazyny.pl, wind farms were also curtailed on 16–21 September. The operator's announcements refer to the Balancing Terms and Conditions.

Compensation for generators

In an announcement of 23 September 2026, PSE confirmed that owners of installations who carried out the instructions are in principle entitled to compensation. The basis is Article 13(7) of EU Regulation 2019/943, Article 9c(7a) of the Energy Law and Article 30(5) and (6) of the Act of 28 July 2023. PSE publishes data on curtailments in 15-minute intervals in the “poze-redoze” report on raporty.pse.pl, and compensation claims are submitted via pse.pl/instalacje-pv.

Background: photovoltaics as the largest technology in the system

The scale of the curtailments results from the structure of the system. According to PSE data for August 2026, discussed by Gramwzielone.pl, total available capacity in the KSE (the National Power System) is around 80 GW, and photovoltaics, with a capacity of 27,545 MW (35%), is the largest technology, ahead of hard coal (22,342 MW) and wind (11,358 MW). In terms of energy production, however, the share of PV is considerably lower: in August it was 21%, compared with 57% for hard coal and lignite combined. From January to August, photovoltaic production rose by 18% year on year.

A warning signal from Greece

The experience of other markets shows how important the pace of energy storage development is. In Greece, production curtailments in 2026 as a whole are expected to exceed 3.5 TWh, and the industry forecasts a 42–43% fall in PV producers' revenues this year. In 2026, Greece will add around 700 MW of storage against 3 GW of new photovoltaics; according to the data cited, standalone energy storage prevented 13.6% of monthly production curtailments.

Significance for the market

  • The risk of curtailment is becoming a permanent element of revenue analysis for photovoltaic farms.
  • PV hybrids with energy storage and standalone storage increase the flexibility of the system and the value of the project.
  • Documenting PSE instructions and submitting compensation claims on time have a direct impact on an installation's financial result.

That is why, in NRG+ projects, analysing the possibility of a PV farm working together with energy storage is a standard element of site assessment.